The Rao Cai is one of the largest rivers in Ha Tinh province. In recent years, floods
have been increasing not only frequency but also intensity and affect to all aspects
of lives. Climate change, improper management of natural resources, inadequate
awareness on flood risk, etc., response for the question ―Why do flood become
increasingly serious?‖. To minimize negative impacts of flood on local people, it is
necessary to make an efficient flood risk management. Flood risk assessment based
on flood modeling has an important contribution to this progress.
To assess flood risk, in this study, the MIKE package including MIKE UHM,
MIKE 11 HD and MIKE 11 GIS, was used to simulate the previous flood events in
2010 and other floods as 0.5% and 0.1%. The main objective of this study is to
develop inundation maps corresponding to the floods as mention above. That is the
foundation to assess the flood risk by overlapping vulnerability and hazard layer. To
assess risk of the flood events, the following conclusions could be depicted as
elements of research procedure:
+ Main reasons and causes of flood in study area are affected by heavy
rainfall with high intensity and more frequency. Those are impact of climate change.
+ Digital Elevation Model (DEM), which represents the floodplain’s surface,
is the input information for simulating and estimating the flooding extend and depth.
The DEM in the research was derived from interpolation of elevation spots and
contour lines of different spatial data such as, contour maps with variable scales,
transportation system maps, dyke system maps, and hydrological maps. The DEM
was built from topography with scale of 1:10,000
94 trang |
Chia sẻ: ngoctoan84 | Lượt xem: 888 | Lượt tải: 0
Bạn đang xem trước 20 trang tài liệu Study on flood risk assessment in downstream area in ke go reservoir, ha tinh province, để xem tài liệu hoàn chỉnh bạn click vào nút DOWNLOAD ở trên
CS
7
Satellite
image
Image. Jpg June 2
nd
2013
4.3.2. Data analysis
4.3.2.1. Hydro-meteorological data
a. Runoff data
The hourly discharge flow into Ke Go reservoir was calculated from water level and
release of Ke Go reservoir based on the water balance equation (shown Appendix
1). The results on hourly discharge flow into Ke Go reservoir of flood event in 2010
and 2013 are shown in Figure 4 - 4 and Figure 4 - 5. The calculated results are used
to setup rainfall runoff model (UHM) to determine model parameters for Ke Go
catchment and sub-basin of downstream area.
37
Figure 4 - 4: Inflow of Ke Go reservoir in October, 2010
Figure 4 - 5: Inflow of Ke Go reservoir in October, 2013
b. Water level
All of water level measuring stations in the study is Cam Nhuong, Do Ho, Thach
Dong which are affected by the tide and are the station measuring water level in
short period from 1970 to present. Besides, there are local stations belong Ke Go
0
500
1000
1500
2000
2500
3000
3500
4000
4500
10/2 10/4 10/6 10/8 10/10 10/12 10/14 10/16 10/18 10/20 10/22
D
is
ch
ar
ge
(m
3/
s)
Time
Inflow of Ke Go reservoir in October, 2010
Inflow
0
50
100
150
200
250
300
350
4000
500
1000
1500
2000
2500
3000
3500
4000
4500
5000
0 5 10 15 20 25
R
ai
nf
al
l
(m
m
)
D
is
ch
ar
g
e
(m
3
/s
)
Hour
Measured rainfall and flood at Ke Go reservoir in
Oct 16th 2013
Rainfall (mm)
Discharge (m3/s)
38
irrigation company to control water level in downstream area when releasing flood
of Ke Go reservoir. They are only measured when flood coming. This thesis
collected water level data all of above station in October, 2010. The main stations
are Phu and Hoi bridges are shown in Figure 4 - 6. They will be used to calibrate
and verify numerical model in next part.
Source: Ke Go Irrigation Company, 2010
Figure 4 - 6: Water level at Phu and Hoi Bridge station in October, 2010
4.3.2.2. Topography data
A significant input for hydrodynamic modeling is the correct representation of
terrain on which the model will work on. To develop DEM the following dataset
were using:
1. Topographic maps of the study area in 1:10,000 scales (measured 2010).
Projection is VN 2000 that was transformed to WGS 1984.
2. The total cross section data along the river of Rao Cai and Gia Hoi is 40 cross
sections, in which Rao Cai has 25, Gia Hoi has 15. These cross sections were
measured in 2011, which are collected from ―Emergency preparedness plans (EPP)
0
0.5
1
1.5
2
2.5
3
3.5
10/4/2010 0:00 10/8/2010 0:00 10/12/2010 0:00 10/16/2010 0:00
W
a
te
r
le
v
e
l
(m
)
Time (hour)
Measured water level at Cau Phu and Cau Hoi in October 2010
Phu Bridge
Hoi Bridge
39
in emergency case of Ke Go Reservoir - Ha Tinh province‖ project of Thuyloi
University.
40
CHAPTER 5: RESULTS AND DISSCUSIONS
5.1. The reasons cause the flooding in downstream area
According to analysis of data about hydro-meteorology, statistic data analysis, flood
and flooding occur more frequently in recently. In this part, thesis will research
reasons caused flooding in downstream of Rao Cai river basin, especially in Ha
Tinh city area.
5.1.1. Climate change impacts
Along with the status of climate change (CC) on the global recently, Ha Tinh
province also has effect of climate change lead to the great disaster suffered more
major effect on the development of socio - economic, military and security.
According to recent researches were done by the Ha Tinh Department of Natural
Resources and Environment, the average temperature in the province increase from
0.1 – 0.2
0
C per decade, the average temperature period 2000-2010 increased more
from 0.3 – 0.6
0
C than 10 - 30 years ago, especially, Huong Khe area increased from
0.7 - 1,4
0
C. Meanwhile, annual rainfall tends reduced greater with variation in terms
of space, time and intensity. Although the rainfall reduces, the intensive of rainfall
caused flooding or flash floods increases. Accordingly, the frequency and regularity
of the storm is also changed, which will be described below. Normally, the rainy
season in Ha Tinh province is from September to November and the storm season is
from July to September. However, recently, the storm season was tends to change
clearly, from August to December. (Hoai, 2009)
Instability in rainfall would cause more severe floods in rainy season and droughts
in dry season. • Increase in frequency and intensity of typhoons, storms would cause
high floods & inundation, flash floods, landslide and erosion. • Increasing water
shortage and growing water demand threaten water supply, water use conflicts. .To
estimate climate change impact cause to flooding in Rai Cai river basin in recent
year based on meteorological data in the study area and surrounding area from 1975
to 2005. Some annual rainfall changes are shown below:
41
Figure 5 - 1: Annual rainfall change on the Rao Cai river basin from 1975 – 2005
In the Figure 5 - 1, in general, the average annual rainfall change of Huong Khe and
Ha Tinh have decrease trend. The decrease of annual rainfall of Ky Anh station is
higher than Ha Tinh ones with 9.42 and 4.03 mm per year period from 1975 to 2005
respectively. This result is suitable with researches of DONRE of Ha Tinh province.
However, rainfall intensive (mm/m, mm/day) have opposite trend. The results
changing of 1 and 3 days maximum rainfalls are shown the following Figure 5 - 2.
y = -4.0289x + 10713
0
500
1000
1500
2000
2500
3000
3500
4000
4500
5000
1975 1980 1985 1990 1995 2000 2005
X (mm)
Year
Ha Tinh station
y = -9.4216x + 21664
0
500
1000
1500
2000
2500
3000
3500
4000
4500
5000
1975 1980 1985 1990 1995 2000 2005
X (mm)
Year
Ky Anh station
42
Figure 5 - 2: Changing of maximum rainfall of Ha Tinh station
Based on rainfall of Ha Tinh meteorological station period from 1975 to 2005, daily
maximum rainfall changes have stable trend or reduce but not much. The trend of
daily maximum rainfall, which indicated various changes (including decrease and
increase) in the first years from 1975 to 1995, ending the period with significantly
increased.
For the maximum rainfall during 3 days shows an increasing trend, this rainfall
duration is main reason cause to flooding in the downstream area. To have an
accurate estimate the data need be updated latest meteorological data.
Interestingly, in recent year although daily maximum rainfall of Rao Cai area in
2010 (455.6mm) is higher than 5 time in 2013 (95mm) however peak flow of Ke
Go reservoir are estimated as equal. Main reason is rainfall in 2013 occurred a few
hours. In addition, maximum rainfall in 2010 and 2013 correspond to frequency
10% and 90%, however, the peak flow of Ke Go reservoir in both year are higher
than design peak flow correspond about 0.5%. Rainfall occurred more frequently
with higher density, especially in short duration.
0
100
200
300
400
500
600
700
1975 1980 1985 1990 1995 2000 2005
X (mm)
Time
Changing of maximum total rainfall in a day
Rainfall Linear (Rainfall)
0
200
400
600
800
1000
1200
1975 1985 1995 2005
X (mm)
Time
Changing of maximum total rainfall in 3 days
Rainfall Linear (Rainfall)
43
Figure 5 - 3: Inflow of Ke Go reservoir and actual rainfall 2013
These results revealed traditional method to calculate design flow for reservoir need
to check again and consider hyetograph or climate change impacts to inflow.
In conclusion, with climate change impact inflow into Ke Go reservoir and flow of
sub-basin in downstream increase, this cause flooding when happening heavy
rainfall.
5.1.2. Infrastructure impacts
Further investigating and finding the main reasons cause this situation is due to the
drainage system in the province of Ha Tinh was built long ago, lack of
synchronized planning, many area seriously degraded, small drainage tunnel cannot
get up when heavy rainfall occur during a long time. On other hand, in the process
of urbanization, cities are focused on building many projects. Besides, the elevation
of some area in HaTinh city is quite low, that might be flooded even when the small
rainfall. The roads can be as a river dyke to keep flood in upstream of river, this
make water level in upstream increased. This issue increase hazard for resident.
5.2. Flood hazard
5.2.1. Rainfall runoff modeling
5.2.1.1 Model setup
Rainfall frequency analysis
Determine statistical characteristics of frequency curve
0
100
200
300
4000
1000
2000
3000
4000
5000
0 5 10 15 20 25
X(mm) Q (m3/s)
Hour
Rainfall and flood at Ke Go reservoir
in Oct 16th 2013
Rainfall (mm)
Discharge (m3/s)
0
1000
2000
3000
4000
5000
6000
0 2 4 6 8 10 12 14 16
Q (m3/s)
Hrs
Design Hydrographs of Ke Go
reservoir
P = 0.5%
P = 0.1%
P = 0.01%
44
Based on the data of daily rainfall of the meteorological stations: Ha Tinh (1975-
2010), Ky Anh (1975- 2006) and Huong Khe (1975- 2006) in Rao Cai river basin
and surrounding, using Pearson type III distribution, daily maximum rainfall
corresponding to various return periods of 1000 and 200 years for each station are
estimated (see Table 5-1).
Table 5 - 1: Result of frequency analysis of maximum daily rainfall
Station
Avg. Rainfall
(mm)
Cv Cs
Daily maximum rainfall corresponding
to return periods (mm)
1000 years 200 years
Ha Tinh 304.8 0.43 0.89 882.6 750.9
Ky Anh 292.6 0.36 0.60 711.6 623.6
Huong Khe 246.7 0.37 0.82 639.7 551.7
Frequency curve of maximum rainfall during 1 day and design rainfall hyetography
of above these are indicated in Appendix 1
Determining design rainfalls
The design rainfall of meteorological stations on Rao Cai river basin are estimated
based on the ratio of actual daily rainfall to design daily rainfall responding to
different frequencies and the actual time distribution of chosen days.
Table 5 - 2: Value of design rainfall distribution of Ha Tinh, Ky Anh and Huong
Khe stations during 1 day corresponding to difference frequency (daily rainfall)
Stations Frequency Type
Day
Ratio
1st 2nd 3th
H
a
T
in
h
0.10%
Actual (15 - 17/10/2010) 132 610 147
1.5
Design 191 883 213
0.50%
Actual (15 - 17/10/2010) 132 610 147
1.2
Design 163 751 182
H
u
o
n
g
K
h
e
0.10%
Actual (15 - 17/10/2010) 53 524 86
1.2
Design 65 640 105
45
Stations Frequency Type
Day
Ratio
1st 2nd 3th
0.50%
Actual (15 - 17/10/2010) 53 524 86
1.1
Design 56 552 90
K
y
A
n
h
0.10%
Actual (13 - 15/10/1984) 85 519 122
1.4
Design 117 712 167
0.50%
Actual (13 - 15/10/1984) 85 519 122
1.2
Design 102 624 146
Definition of sub-basin of Rai Cai river basin
The MIKE - UHM was used to calculate lateral inflow.
In order to develop lateral inflow of sub-basins corresponding to rainfall frequencies,
MIKE - UHM (SCS) model is used. The results of this model are input for MIKE
11 HD as point source in downstream area in river network.
The sub-catchment delineations and their tributaries (i.e. areas, average surface
elevation and slope) were initially calculated from the DEM using the spatial
extension tools of ArcGIS software. The UHM model for sub-basin are considered
land use, elevation, slopes, and drainage system, also included for schematization as
shown in (Figure 5 - 4).
Figure 5 - 4: Rao Cai watershed sub-basin schematizations and Thiessen polygon
weighting computation of mean rainfall of sub-catchment in Rao Cai river basin
Meteorology Station
46
The spatial distribution of rainfall for Ke Go reservoir catchment and sub-catchment
in downstream area was calculated based on the Thiessen polygon concept. And the
results have shown in Table 5 – 3.
Table 5 - 3: Sub-catchment of Rao Cai river basin and weighting factors of
meteorological station
No
Sub-
catchment
Area
(km
2
)
Weighting factor of
each station
Description
Ha
Tinh
Ky
Anh
Huong
Khe
1. Sub 1 223 0.59 0.20 0.20 Ke Go. Reservoir
2. Sub 2 65.93 1
Downstream Ke Go
Reservoir to junction of
Ngan Mo
3. Sub 3 70.58 1
Ngan Mo to Cau Ho on Gia
Hoi river
4. Sub 4 57.80 0.93 0.07 Quen Catchment
5. Sub 5 255.73 0.08 0.92 Rac Catchment
6. Sub 6 49.39 1
Ngan Mo to Cau Phuon
Ngan Mo river
7. Sub 7 80.55 1 Bang river
8. Sub 8 39.66 1 Thach Dong estuary
9. Sub 9 58.55 1 Cam Cua Nhuong
5.2.1.2 Calibration and verification of MIKE_RR UHM model for Ke Go reservoir
catchment
Calibration
The area of Ke Go reservoir catchment is 223 km
2
. In order to calibrate MIKE RR
UHM for this catchment, the hourly rainfall and discharge at Ke Go reservoir from
Oct 4
th
to 11
th
Oct 2010 were used to compare between measured and calculated
data. The parameters and initial condition are determined (Figure 5 - 5) based on the
criteria such as (Coefficient of efficiency (NASH) and volume error, peak time
error).
47
Figure 5 - 5: Parameters of UHM in MIKE RR model of Ke Go catchment
Table 5 - 4: Parameters of UHM in MIKE RR model of Ke Go catchment
Parameters Base flow: BF
Loss Curve
number: CN
Initial AMC:
IAMC
Time lag: TL
Indicators m
3
/s - mm Hours
Value 10.3 60 2 0.5
Figure 5 - 6: Observation and simulation of hourly discharge of Ke Go reservoir
from 2 Oct to 6 Oct – 2010 for calibration model
48
Table 5 - 5: Different in peaks of observed and simulated discharge for calibration
mode at Ke Go reservoir
Calibration
Q Max
(m
3
/s)
ΔQ (m
3
/s) Time (hr) Δt (hrs) R
2
Observed 2020 -140
(7%)
22 AM 4/10/2010
0 0.75
Simulated 1880 22 AM 4/10/2010
Verification
The discharges of Ke Go reservoir from 14th to 19th of October, 2010 were used to
verify parameters of model, which are determined in the calibration step. The
calculated and simulated hydrograph at Ke Go reservoir during flood event are
illustrated in Figure 5 - 7. The different of peaks of observed and simulated
discharge in verification model at Ke Go reservoir is shown in Table 5 - 6.
Figure 5 - 7: Observed and simulated hourly discharge of Ke Go reservoir from 14
Oct to 19 Oct – 2010 – Verification
Table 5 - 6: Different in peaks of observed and simulated discharge in verification
at Ke Go reservoir
49
Calibration
Peak of
discharge
(m
3
/s)
Different:
ΔQ (m
3
/s)
Time of peak
hrs
Different
Δt (hrs)
R
2
Observed 3980 190
(5%)
16 AM 16/10/2010
0 0.76
Simulated 4170 16 AM 16/10/2010
In calibration and verification model step, the calculated and measured data are fit
well as shown Figure 5 – 6 and Figure 5 – 7. Following Table 5 - 5 and Table 5 - 6,
the different of measured and calculated data in the peak flow is trivial, 7% for
calibration model and 5% for verification model. The time of peak in the
measurement and calculation are coincident. The coefficient of efficient (NASH) of
the calibration and verification step is higher than 0.7. Therefore, the determined
parameters are acceptable for Ke Go reservoir catchment and surrounding area to
simulate discharge.
In addition, discharge flow into Ke Go reservoir in October 16
th
2013 is run with the
verified rainfall runoff model for and the results are shown below.
Figure 5 - 8: Flood at Ke Go reservoir in 16 October 2013
In general, the results of the simulation on the Ke Go reservoir are quite good.
Although some time the observed and calculated data are not fit and water balance
50
error is still high accounting for 28.1%. The results might be affected by local
rainfall, hence the pre-process of input data for Rainfall runoff model is necessary.
Determining parameters of Rainfall runoff model for sub-basin of Rao Cai river
basin.
In the downstream area of Ke Go reservoir and its tributaries, there is no
hydrological station for discharge data. Therefore, the lateral inflow corresponding
to actual flood, design hydrograph was calculated based on the rainfall data UHM
model, which rainfall data and parameters obtain from typical sub-basin. In the
study area, the Ke Go catchment has similar characteristics with the sub-basins in
term of about soil condition, plant cover, land use, geology and meteorology. Thus,
the parameters of UHM-SCS model for Ke Go catchment are used to determining
parameter for sub-basins in Rai Cao River by adjustment. Besides, the land use
condition of each sub-basin is considered.
Table 5 - 7: Parameters of UHM - SCS for Rao Cai’s sub-catchments
No Sub-catchment Area (km
2
)
Parameter (CN)
BF
(m
3
/s)
CN
IAMC
(mm)
TL
(hrs)
1. Sub 2 65.93 3 74 2 1
2. Sub 3 70.58 3 74 3 1
3. Sub 4 57.80 5 74 2 1
4. Sub 5 255.73 10.2 74 3 0.5
5. Sub 6 49.39 3 91 2 1
6. Sub 7 80.55 3 74 2 1
7. Sub 8 39.66 3 74 2 1
8. Sub 9 58.55 3 74 2 1
The discharge of sub-basin is calculated by MIKE – UHM model, are connected to
main river based on their location of sub-basins.
5.2.2. Flood modeling
5.2.2.1. Setup MIKE 11 HD model
To simulate flooding by MIKE 11 HD model, the following data are required: river
network including profiles (shape, roughness, structure, etc.); Digital elevation
51
model (DEM) to determine floodplain; Hydraulic boundary and initial conditions;
Measured water level and inflow of sub-catchment.
River network
Hydraulic diagram is established based on the river network documents
containing Gia Hoi, the Rao Cai river behind Ke Go dam.
Figure 5 - 9: Hydraulic calculation network in downstream of Ke Go reservoir
Topography
Cross sections
Whole network has 70 cross sections. Cross-sections are specified by a number of
x-z coordinates where x is the transverse distance from a fixed point (often left bank
top) and z is the corresponding bed elevation. All of cross sections were obtained
from Institute of Civil Engineering of Thuy Loi University which measured data in
2011. The missing data were interpolated from measured value river bed, DEM and
topography in 10,000 scales.
Floodplain
Land elevation in the downstream range from 2.5 to 10 m, so when big flood and
heavy rainfall, the river can’t stand for big discharge. This issues cause overland
along the river. In floodplain during flood event, 1D model is not adequate to
52
describe the spatial variable of overland, water depth, velocity, etc. However, to
solve these limitations of the MIKE 11 model, the floodplain via structure or sub-
branch can be setup. In this study, floodplain was setup via weir side with storage
capacity, the crest of weir was determined by overflow threshold. In downstream
have 8 sub- catchments, and each sub-catchment has different overflow threshold. It
depends on their topography. Each floodplain is determined by storage capacity,
length of weir and overflow threshold.
Figure 5 - 10: Storage capacity of floodplain in downstream
Determining boundary conditions of the model
- Upstream boundary are release of Ke Go reservoir corresponding to actual
flood in 2010 and different design floods obtain from the Establishing Ke Go
reservoir operation regular in 2012.
- Downstream boundaries are hourly water level at the Thach Dong
hydrological station (Cua Sot) and the Cam Nhuong hydrological station (Cua
Nhuong)
- Lateral inflows are calculated by rainfall-runoff models in above part. The
downstream of Ke Go reservoir is divided into 8 sub-catchments, which are linked
along the major river systems and tributaries.
0
2000
4000
6000
8000
10000
12000
14000
0 1 2 3 4 5
W
(
h
a)
Z (m)
Z ~ W
Sub9
Sub8
Sub2
Sub3
Sub4
Sub5
Sub6
Sub7
53
Table 5 - 8. Runoff link of sub-catchments into river network in MIKE 11 model
No
Sub-
catchment
Area
(km
2
)
Description
Link
1. Sub 2 65.93
Downstream Ke Go
Reservoir to junction of
Ngan Mo
Raocai (0m – 7000m)
2. Sub 3 70.58
Ngan Mo to Cau Ho on
Gia Hoi river
Giahoi (0m-14700m)
3. Sub 4 57.80
Quen Catchment
(Thuong Tuy Cat)
Giahoi (28500m)
4. Sub 5 255.73 Rac Catchment Giahoi (31231m)
5. Sub 6 49.39
Ngan Mo to Cau Phuon
Ngan Mo river
Raocai (7000m-24000m)
6. Sub 7 80.55 Bang river Raocai (24000m-36200m)
7. Sub 8 39.66 Thach Dong estuary Raocai (36200m-43210m)
8. Sub 9 58.55 Cam Cua Nhuong Giahoi (31231m-33210m)
- Checking boundary: At the downstream area of Ke Go reservoir, during
flooding season, the Ke Go irrigation company usually arranges water level
measurement stations in the downstream area to monitoring the process of releasing
flood through operating spillways to ensure minimizing the downstream inundation.
The positions of the water level measurement at the downstream area of Ke Go
reservoir: Vang Vang trough, Cau Ngan Mo, Rao Cai trough, Rao Na, Cau Phu,
Cau Hoi... In the thesis, two measurement stations at the Cau Phu and the Hoi
bridge are used as checking stations.
The collected data of the water level at the downstream area of Ke Go
reservoir at the above locations are not continuous. Therefore, the simulated data
will be extracted corresponding to available measurement data to analysis.
Table 5 - 9: Monitoring points for the calibrating and verifying hydraulic model
No Measuring point River Chainage (m)
1 Cau Phu Rao Cai Raocai 23421
2 Cau Ho Gia Hoi Giahoi 13684
54
5.2.2.2 Calibration and verification of the MIKE 11 HD model
Calibration
The most sensitive parameter of the MIKE 11 HD model is roughness
coefficient (n or M). It is a very important parameter and greatly influenced on the
study results. In this thesis, the roughness coefficient was estimated based on the
topographic documents associated with field investigation to calculate. The
roughness coefficient is in the range from 0.022 to 0.031 with the natural river (see
Appendix 3).
The results of model adjustment are presented under in form of charts and the
maximum value between the results of calculated and measured at the checking
locations. The results of calculated and measured water level at the checking stations
are presented in the Figure 5 - 11, Figure 5 - 12. (Blue line is calculated values and
black points are measured values).
Figure 5 - 11: Calculated and measured water level at Cau Phu (2
nd
to 6
th
October,
2010)
55
Figure 5 - 12: Calculated and measured water level at Cau Ho (2
nd
to 6
th
October,
2010)
Table 5 - 10: Results of flood simulation form 2
nd
Oct to 6
th
Oct, 2010 for
calibration of MIKE 11 HD model
No
Checking
location
River
HMax (m) Difference
(m) Calculated Measured
1 Cau Phu Rao Cai 2.6 2.73 0.13
2 Cau Ho Gia Hoi 2.39 2.40 0.01
The results of the simulation of the Rao Cai river and Gia Hoi river:
corresponding to available measurement data:
+ The line of the water level process between the calculation and
measurement is relatively similar in terms of fluctuation phase and the peak value;
the line of process shown the fluctuation of the tidal effect.
+ The difference of the higher water level is not significant with the fluctuated
value ranging from 0.01 to 0.13 m. The difference of peak flow at the checking stations
is in admissible range.
Verification model
After calibration of model, the model was run for flood from12 October to 18 October –
2010 to verify
56
The results of model testing is also presented on the chart about the process of
the properly measured water level at the checking stations in the network, combining
with corresponding testing target.
The results of the calculated and measured data at the checking stations are shown in the
Figures 5 – 13.
Figure 5 - 13: Calculated water level and measured water level at Cau Phu(12 Oct
to 18 Oct- 2010)
Figure 5 - 14: Calculated water level and measured water level at Hoi Bridge (12
Oct to 18 Oct- 2010)
57
The different of the peak flow shown in the following table 5 - 11:
Table 5 - 11: Results of flood simulation from 12 Oct to 18 Oct- 2010
No.
Checking
location
River
HMax (m) Difference
(m) Calculation Measurement
1 Cau Phu Rao Cai 3.25 3.10 0.14
2 Cau Ho Gia Hoi 2.90 3.02 0.12
- The simulation results were quite consistent with the real data in term of the
flood events occurred in the recently. That is, the parameters used in the hydraulic
model are acceptable flood simulation of the system river of Rao Cai river basin.
The model might be used to conduct the hydraulic calculations under the different
scenarios for the study area.
5.2.2.3. Simulations of various return periods of flood events
To calculate design flood in the downstream of the Ke Go reservoirs, this thesis
assumed that the frequency of design flood of Ke Go reservoir and frequency of
rainfall are the same. Water level at the downstream will use actual data of 2
hydrological stations (Cam Nhuong and Thach Dong) from 16 Oct to 18 Oct – 2010.
The simulation of flood flow using calibrated MIKE 11 HD mentioned above, are
done. The period of flood simulation is five days, assuming that flood occur from 1
Oct to 5 Oct - 2010.
The simulated water level at Cau Phu and Cau Hoi station corresponding to flood
periods are in Table 5 - 12.
Table 5 - 12: Maximum water level corresponding to design and checking flood of
Ke Go reservoir
(Unit: m)
Station Chainge (m) Design flood Checking flood
Cau Ho Giahoi 2001.42 3.52 4.15
Cau Phu Raocai 4988.87 3.73 4.25
58
Based on results of maximum water level at Cau Ho and Cau Phu, the water level in
Cau Phu is higher than Cau Ho. The difference of the maximum water level
between design and checking flood about 0.5 m.
5.2.3. Flood hazard maps
There are many methods to carry out flood risk assessment based on different
applied modeling. In this research, the author selected MIKE 11 GIS is a tool for
the spatial presentation and analysis of one-dimensional (1D) flood model results
for use in the flood risk assessment process. The MIKE 11 GIS system integrated
the MIKE 11 with the spatial analysis capabilities of the ArcView Geographic
Information System (GIS) gives us an advanced tool to assess flood risk. The
outputs were developed from using MIKE 11 GIS are important inputs for a range
of floodplain management undertakings including flood risk assessment, flood
control, flood forecasting, floodplain preservation and restoration, etc.,
The software requirements for developing inundation maps based on using MIKE
11GIS include MIKE 11 HD and ArcGIS. Alternately, in the research, some steps
in building up flood risk maps, ArcGIS is evolved to visualize more clearly the
pictures of flood.
To assess hazard of flooding, a hazard level scale is defined on the basis of the
flooding depth. A grid including four levels (low, medium, high, and very high) of
flooding depth would be created. Areas inundated under 3m or deeper water will be
recognized as very high hazard area. An area with 1.5-3m, 0.5-1.5m, and lower
0.5m deep of flooding depth will get high, medium or low hazard area, respectively.
As a result, thesis has four different hazard levels defined as in the follow table:
Table 5 - 13. Designed flooding hazard level scale for the downstream of the Ke Go
reservoir
No Flood depth (m) Hazard zone
1 < 0.5 Low (1)
2 0.5 – 1.5 Medium (2)
3 1.5 – 3 High (3)
59
No Flood depth (m) Hazard zone
4 > 3 Very high (4)
Flood hazard threshold are divided 4 levels, which were depended on impact
thresholds of flooding depth to person. The flooding depth is less than 0.5 m
correspondence to low hazard. This value approximates the height of leg of adult
people so when the flood comes they adapt with them and can help people around
them especially the child and the old. The flooding depth is less than 1.5 m
equivalent to medium hazard level. This value approximates the height of body of
adult people. Beside in the center part of Vietnam, resident often have flooding
mitigation measure by building small flat far from the land around 1.5 m to avoid
flood or hide livestock (big, chicken, dog, cat). And for flooding depth is 3 m,
this value is as the same the height of first floor of building level 2 or 3 (such as
house publics school, clinic, house’s resident). When flooding, people often hide
in building level 2 or 3, if flood level can reach this value people can move to
upstairs.
a) Low hazard level
b) Medium hazard level
c) High hazard level
d) Very high hazard level
~ 1.5 m
60
Figure 5 - 15. Some typical picture to determine flood hazard threshold
5.2.3.1. Hazard map of Flood event in 2010
Figure 5 - 16. Flood hazard map for historical flood event in 2010
With differences of water depth, inundation map is classified into four groups: very
high, high, medium, and low. Most of inundated areas have water depth lower 2 m
and 3 m. These groups occupy three-fourths of whole inundated extent. High and
very high hazard area in the term of inundation distribute along main river (Rao
Cai) and a part of Bang river.
Table 5 - 14. Flood hazard areas for flood event in 2010
Hazard zone
Design flood
Area (km
2
) Percentage (%)
Low 24.8 6.6%
Medium 94.8 25.1%
61
High 218.2 57.8%
Very high 39.9 10.6%
5.2.3.2. Hazard map of 0.5% and 0.1% flood
Figure 5 - 17. Flood hazard map of 0.5% design flood event
62
Figure 5 - 18. Flood hazard map of 0.1% design flood event
Table 5 - 15. Flood hazard areas corresponding to design and checking flood
Hazard
zone
Design flood Checking flood
Area (km
2
) Percentage (%) Area (km
2
) Percentage (%)
Low 31.3 7.5% 30.6 6.7%
Medium 96.9 23.3% 97.3 21.3%
High 232.4 56.0% 257.3 56.5%
Very high 54.6 13.2% 70.5 15.5%
5.3. Flood vulnerability
There are various methods to determine vulnerability. One method is to use a
vulnerability scale which is defined via the consideration of the defined hazard
scenarios and the information available regarding the damage to the population and
environment. In this study, vulnerability map was built on the basis of population
density map.
63
Figure 5 - 19: Frequency distribution of population of study area
Figure 5 - 20: Frequency distribution of population density of study area
Following Figure 5 - 19 and Figure 5 - 20, population number of communes in Rao
Cai river basin range from 1905 to 9875 people. The difference about population
number between communes is not much with population distribution in Rao Cao
river basin is estimated based on quite frequency have normal distribution type. For
population density is quite different because this value depends on area and
population of commune. It normally middle and mountain zone have large area but
a few populations, is opposite in delta or city center. So criteria to divide
vulnerability levels to ensure area for different level are equal.
Table 5 - 16. Criteria of vulnerability map derived from population density for the
downstream of the Ke Go reservoir
64
No
Population density
(Person/km
2
)
Vulnerability level
1 < 100 Low (1)
2 100 – 500 Medium (2)
3 500 – 1500 High (3)
4 > 1500 Very high (4)
Figure 5 - 21: Vulnerability map in Rao Cai river basin
Results determine vulnerability zone, high zone located in Ha Tinh province and
some medium zone located in around vulnerability. A few areas are very high zone,
because there is high density population. Based on vulnerability map, the
population often lives near in the city center and coastal area.
65
5.4. Flood risk in downstream area of the Ke Go reservoir
To assess flood risk in the downstream of Ke Go reservoir, a flood risk matrix is
derived from flood hazard level and flood vulnerability level. As a result of hazard
and vulnerability assessment, flood risk scale will be created by four levels of
hazard and four levels of vulnerability (low, medium, high and very high). The
resulting risk level scale consists of 4x4 = 16 cells and includes four different levels
of risk: low, medium, high and very high (see the follow figure).
Figure 5 - 22. Designed risk level for the downstream of the Ke Go reservoir
H
az
ar
d
l
ev
el
Low (1) 1 2 3 4
Medium (2) 2 4 6 8
High (3) 3 6 9 12
Very high (4) 4 8 12 16
Low (1) Medium (2) High (3) Very high (4)
Vulnerability level
Table 5 - 17. Criteria of vulnerability map derived from population density for the
downstream of the Ke Go reservoir
No Criteria Risk zone
1 1 – 3 Low
2 4 – 6 Medium
3 8 - 9 High
4 12 - 16 Very high
Flood risk scale is the basis to develop flood risk map. Flood risk map is the
combination of hazard map and vulnerability map which can describe
comprehensively risky statement of study area, where was recognized as a flood-
heavily-impacted area.
Table 5 - 18. Flood risk map for the downstream area of Ke Go catchment in flood
in October, 2010
Risk zone Area (km
2
) Percentage (%)
66
Risk zone Area (km
2
) Percentage (%)
Low 52.7 14.0%
Medium 164.5 43.6%
High 107.6 28.5%
Very high 52.8 14.0%
Total 377.6 100%
The below map shows the potential risk which was caused by 2010 flood event. In
general, risk areas are nearly medium and high level, with above 70% affected area
while low risk area and high risk area were equal with 14% affected area. The
medium risk area reached 164.5 Km
2
approximately 43.6% (the highest), where
located almost along Rao Cai river near Ha Tinh city and surrounding area.
Figure 5 - 23. Flood risk map for the downstream area of Ke Go river basin of
flood in October, 2010
67
Flood risk map for design flood and checking flood with 200 year and 1000 year
return period was built by intersecting hazard map and population density map to
give an assumption how is risky if 0.1% and 0.5% flood occurs at the moment. It
does not mean that this map will depict exactly risk situation in future due to
changing of population distribute land use, demographic density and other aspects
as well.
Figure 5 - 24. Flood risk map for 0.5% design flood
68
Figure 5 - 25. Flood risk map for 0.1% checking flood
Table 5 - 19. Statistic table of flood risk of different floods
Hazard
zone
Design flood Checking flood
Area (km
2
) Percentage (%) Area (km
2
) Percentage (%)
Low 70.0 16.9% 64.4 14.1%
Medium 164.4 39.6% 178.9 39.3%
High 112.3 27.0% 123.5 27.1%
Very high 68.5 16.5% 88.9 19.5%
Total 415.1 455.7
Following Table 5 - 19 shows risk areas, at four different levels correspond to
design and checking flood of Ke Go reservoir. Overall, the total risk area of
checking flood case is higher than design flood case because flow of the former is
higher than last one. Medium and high risk areas are nearly total affected area with
above 70%. In both case, percentage of affected medium and high area were equal
with 39 % and 27% respectively. Only having change in low area and very high
area.
69
The statistical results of table 5-15, figure 5-17 and figure 5-18 show that the
flooding depth in downstream area of Ke Go reservoir is quite severe. Because this
is an important area, there is a need to prepare some effective measures to minimize
damages to the Ha Tinh city and surrounding area. To flood risk management, we
can use structural and non-structural measures. The structural measures can design
dykes or build levees along Rao Cai and Gia Hoi rivers. At the present, a number of
measures are applied all over the world to ensure safety for particularly important
areas. The nonstructural measures are structure elevation or structure relocation by
moving structure in low land to high land. Beside, awareness increase of resident
about flood control and mitigation solution is very important in flood risk
management.
70
CHAPTER 6: CONCLUSIONS AND RECOMMENDATIONS
6.1. Conclusions
The Rao Cai is one of the largest rivers in Ha Tinh province. In recent years, floods
have been increasing not only frequency but also intensity and affect to all aspects
of lives. Climate change, improper management of natural resources, inadequate
awareness on flood risk, etc., response for the question ―Why do flood become
increasingly serious?‖. To minimize negative impacts of flood on local people, it is
necessary to make an efficient flood risk management. Flood risk assessment based
on flood modeling has an important contribution to this progress.
To assess flood risk, in this study, the MIKE package including MIKE UHM,
MIKE 11 HD and MIKE 11 GIS, was used to simulate the previous flood events in
2010 and other floods as 0.5% and 0.1%. The main objective of this study is to
develop inundation maps corresponding to the floods as mention above. That is the
foundation to assess the flood risk by overlapping vulnerability and hazard layer. To
assess risk of the flood events, the following conclusions could be depicted as
elements of research procedure:
+ Main reasons and causes of flood in study area are affected by heavy
rainfall with high intensity and more frequency. Those are impact of climate change.
+ Digital Elevation Model (DEM), which represents the floodplain’s surface,
is the input information for simulating and estimating the flooding extend and depth.
The DEM in the research was derived from interpolation of elevation spots and
contour lines of different spatial data such as, contour maps with variable scales,
transportation system maps, dyke system maps, and hydrological maps. The DEM
was built from topography with scale of 1:10,000.
+ For the, in order to simulate the lateral inflow of sub-catchments in
downstream of Ke Go reservoir, the regionalization method was applied by using
the model parameters of Ke Go catchment;
71
+ The combination of flooding depth (hazard factor) and population density
(vulnerability factor) with the weighing factors for both of them, flood risk
assessment was done and mapped. The level of hazard and risk were determined for
each community in Cam Xuyen, Thach Ha and Ha Tinh city. These maps can be
used for flood management.
6.2. Recommendations
Due to limited time and knowledge, this thesis have focused on simple hazard and
vulnerability such as flooding depth and population density, to have valuable result
we have to considering to other aspect such as: velocity, during flooded (hazard
factor) and vulnerability about agriculture, infrastructure (road, railway). Besides
to improve result flood simulation, inundation map need good data, in study area
are almost data from local supply (water level at upstream, downstream, release
flow of Ke Go reservoir, which can be reedited for an another reason (political, )
From this study, the following issues are strongly recommended:
- Technical issues: Before using the recorded data of a station, it is necessary to
firstly check the data for continuity and consistency.
- Research issues: flood risk assessment is difficult but necessary for flood risk
management and the results of hazard and risk assessment should be represented to
the local and regional decision makers.
Recommendations for future research:
The results of flood modeling and flood characteristics can be improved if
better resolution and quality DEM is used for flood simulation. Research was based
on the topography in 10,000 scales. The usage of better resolution and quality DEM
and considering infrastructure such as road, railway, and building or using
satellite image and classify image of past flood to improve quality of hydrodynamic
model are topic for future research.
Besides, it is undeniable that awareness of resident about flood it is very
important in flood control and mitigation and it is effect to result flood risk.
72
The study of flood hazard should be more considering with others scenarios to
obtain the higher results of risk assessment for the region in order to quantify the
expected damage for different return periods.
Recommendations for the Local Administrative Authorities and local communities:
It should be improved the risk perception of local community regarding to
flood process and its hazardous effect on population and their property.
New hazard maps should be represented to the population and they should be
informed about probable results. According to of European Union, the risk maps
should be rebuilt after 5 years.
It should be prohibited to use dikes for cattle pasture.
Dikes should be built up to protect population along rivers
Construction of small channels and rising vines with ground will decrease the
water level on cultivated land and protect it from inundation.
Raising the awareness of people about flood, hazard and mitigation ways
73
REFERENCES
Alkema, D. (2007). Simulating floods: on the application of a 2D hydraulic model
for flood hazard and risk assessment. ITC Dissertation; 147, ITC: 198.
Asian Disaster Reduction Center (ADRC). (2005). Total disaster risk management-
Good practices 2005.
Baas, S., Ramasamy, S., DePryck, J. D., Battista, F. (2008). Disaster Risk
Management Systems Analysis. Environment, Climate Change and Bioenergy
Division, FAO, Rome, Italy, 68 pp.
Bell, F. (1999). Geological hazards: their assessment, avoidance and mitigation.
London: E & FN SPON.
Bruijn, K. M. D., Klijn, F. (2005). Resilient flood risk management strategies. Delft
University of Technology WL|Delft Hydraulics.
Central committee for flood and storm control (CCFSC). (2013). Statistics of flood
and tropical in Vietnam in 2013.
Commonwealth Scientific and Industrial organisation (CSIRO). (2000). Annual
report. In: Jennifer North , k. R. (ed.) Campbell: CSIRO.
Chien, N. (2010). Dam Safety in major flood conditions, Thuy Loi University
Chow, V. T., Maidment, D. R., Larry W. Mays (1964), Applied Hydrology,
McGraw-Hill,
Delft. (2014). Deltares enabling Delta life. Delft: Delft Hydraulics.
DHI. (2011). MIKE 11 User Guide. Denmark: DHI.
Federal emergency management agency (FEMA). (2010). Flood Hazard Mapping
Web Site. Retrieved 3 2014, from from
74
Geohazards. (2009). Applied earth Sciences:Geo Hazards,Process Modelling Multi
Hazard risk . ITC.
Hawkins, R.H.; Jiang, R.; Woodward, D.E.; Hjelmfelt, A.T.; Van Mullem, J.A.
(2002). "Runoff Curve Number Method: Examination of the Initial Abstraction
Ratio". Proceedings of the Second Federal Interagency Hydrologic Modeling
Conference, Las Vegas, Nevada (U.S. Geological
Survey). doi:10.1111/j.1752-1688.2006.tb04481.x. Retrieved 24
November 2013
Ha Tinh. (2014, 6). Ha Tinh genneral infomation. Retrieved 2014, from
HCFSCS, 2011, Annual damage report of Ha Tinh province in 2010, Ha Tinh.
Hec-Ras. (2010). HEC-RAS v4.1 User Manual.. US Army Corps of Engnieers, USA
Hieu, T. H. (2012). Ha Tinh city "flooded" after the rainfall. Retrieved July 2014,
from
con-mua-keo-dai-48428.html
Hoai. A. T. (2009). Biến đổi khí hậu ở Hà Tĩnh - Thực trạng và giải pháp.
Retrieved January 2014, from
khi-hau-o-ha-tinh-thuc-trang-va-giai-phap/54003
Hoai, N. T. (2013). 2013: 264 people dead and missing due to floods. Retrieved
January 2014, from
nguoi-chet-va-mat-tich-do-bao-lu-c17a141981.html
International Strategy for Disaster Reduction (ISDR) (2004). Living with Risk - A
global review of disaster reduction initiatives. International Strategy for
Disaster Reduction. New York, UN/ISDR. 2: 429.
Ke Go Irrigation Company (KGIC) . (2012). Operation process of Ke Go reservoir,
2012
75
Kumpulainen, S. (2006). "Vulnerability concepts in hazard and risk assessment.
Natural and technological hazards and risks affecting the spatial development
of European regions." Geological Survey of Finland Retrieved Special Paper,
from
Klijn, F., M. van Buuren, et al. (2009). "Flood-risk Management Strategies for an
Uncertain Future: Living with Rhine River Floods in The Netherlands?"
AMBIO: A Journal of the Human Environment 33(3): 141-147.
Merz, et al. (2007). Flood Risk Mapping At The Local Scale: Concepts and
Challenges. Flood Risk Management in Europe. Springer Netherlands, 25:
231-251.
Plate, E. J. (2002). Flood risk and flood management. Journal of Hydrology 267(1-
2): 2-11.
Pender, G. and S. Néelz (2007). "Use of computer models of flood inundation to
facilitate communication in flood risk management." Environmental Hazards
7(2): 106-114.
Thai, N. C., Lan, P. T. H., Huan. T. N. (2011). Study effects of dam breaking at Ke
Go reservoir – Ha Tinh in downstream area. Water Resources and
Environment Journal, Thuy loi University, Vol. 11, pp 18 - 25.
Thong, L. Q., (2014). Study on effect of wave to Ke Go emergency dam. Master
thesis of Thuyloi university, Vietnam.
Twigg, J. (2004), Disaster risk reduction: Mitigation and Preparedness in
development and emergency programming. Humanitarian Practice Network.
London Kingdom.
76
Tamar Tsamalashvili. (2010). Flood risk assessment and mitigation measure for
Rioni River, University of Twente;
Tu, V. T . (2009). Flood inundation, damage and risk assessment in Hoang Long
basin, Vietnam, AIT Dissertation, Asian Institute of Technology
United States Department of Agriculture (USDA) (1986). Urban hydrology for
small watersheds. Technical Release 55 (TR-55) (Second Edition ed.). Natural
Resources Conservation Service, Conservation Engineering Division.
USGS. (2013). Satellite image of Ha Tinh area
USGS. (2011). DEM of Ha Tinh area,
Vi, D. N. (2013). Nhìn lại 8 trận lụt kinh hoàng tại Việt Nam. Retrieved January
2014 from
nam.2.456814.htm
Viet, T. Q. (2009). Flood risk assessment for the Thach Han river basin, Quang Tri
province, Vietnam. Cologne University of applied science.
Vietnam Water Resources Assistance Project (VWRAP). (2003). Feasibility study
for modernization of Ke Go project, Ha Noi, Haskoning.
Vnexpress. (2010). Miền Trung vật lộn với lũ dữ nhất 10 năm. Retrieved January
2014 from
nhat-10-nam-2896392.html
Vnexpress. (2013). The flooding in Oct, 2013 in central Vietnam. Retrieved January
2014 from
https://www.google.com/maps/d/u/0/viewer?mid=zGR_qj798D2c.kLUgSscZ
XoJk&msa=0&iwloc=0004e8ea5f790918f950c
77
APPENDIX
Appendix 1: Frequency curve of maximum rainfall during 1 day of stations
Hyetograph of design rainfall of Ha Tinh stations corresponding to 1000 years
return period
Hyetograph of design rainfall of Ha Tinh stations corresponding to 200 years
return period
0
100
200
300
400
500
600
700
800
900
1000
1st 2nd 3th
R
ai
n
fa
ll
(m
m
)
Time (day)
Actual
Design
0
100
200
300
400
500
600
700
800
1st 2nd 3th
R
ai
n
fa
ll
(m
m
)
Time (day)
Actual
Design
78
Hyetograph of design rainfall of Ky Anh stations corresponding to 1000 years
return period
Hyetograph of design rainfall of Ky Anh stations corresponding to 200 years
return period
0
100
200
300
400
500
600
700
800
1st 2nd 3th
R
ai
n
fa
ll
(m
m
)
Time (day)
Actual
Design
0
100
200
300
400
500
600
700
1st 2nd 3th
R
ai
n
fa
ll
(m
m
)
Time (day)
Actual
Design
79
Hyetograph of design rainfall of Huong Khe stations corresponding to 1000 years
return period
Hyetograph of design rainfall of Huong Khe stations corresponding to 200 years
return period
0
100
200
300
400
500
600
700
1st 2nd 3th
R
ai
n
fa
ll
(m
m
)
Time (day)
Actual
Design
0
100
200
300
400
500
600
1st 2nd 3th
R
ai
n
fa
ll
(m
m
)
Time (day)
Actual
Design
80
FFC 2008 © Nghiem Tien Lam
30
130
230
330
430
530
630
730
830
930
1030
1130
0.01 0.1 1 10 20 30 40 50 60 70 80 90 99 99.9 99.99
FREQUENCY CURVE OF MAXIMUM RAINFALL DURING 1 DAY - HA TINH STATION
R
a
in
fa
ll,
X
(m
m
)
Frequency, P(%)
Maximum rainfall during 1 day
TB=304.81, Cv=0.41, Cs=0.86
Pearson Type III Distribution
TB=304.81, Cv=0.43, Cs=0.89
© FFC 2008
FFC 2008 © Nghiem Tien Lam
20
120
220
320
420
520
620
720
820
920
0.01 0.1 1 10 20 30 40 50 60 70 80 90 99 99.9 99.99
FREQUENCY CURVE OF MAXIMUM RAINFALL DURING 1 DAY OF KY ANH
R
a
in
fa
ll
(m
m
)
Frequency, P(%)
Ky Anh_Maximum rainfall during 1 day
TB=292.62, Cv=0.36, Cs=0.60
Frequency curve of maximum rainfall during 1 day of Ky Anh
TB=292.62, Cv=0.36, Cs=0.60
© FFC 2008
FFC 2008 © Nghiem Tien Lam
40
90
140
190
240
290
340
390
440
490
540
590
640
690
740
790
0.01 0.1 1 10 20 30 40 50 60 70 80 90 99 99.9 99.99
FREQUENCY CURVE OF MAXIMUM RAINFALL DURING 1 DAY OF HUONG KHE
R
a
in
fa
ll
(m
m
)
Frequency, P(%)
maximum rainfall during 1 day of Huong Khe
TB=246.72, Cv=0.37, Cs=0.62
frequency curve
TB=246.72, Cv=0.37, Cs=0.82
© FFC 2008
81
Appendix 2: Roughness coefficient
River Chainage (m) Manning (n)
Raocai 0 0.03
Raocai 1382 0.031
Raocai 2676 0.031
Raocai 3593 0.029
Raocai 4558 0.029
Raocai 4638 0.029
Raocai 5588 0.029
Raocai 6576 0.029
Raocai 7951 0.029
Raocai 9651 0.024
Raocai 11438 0.024
Raocai 15969 0.024
Raocai 26702 0.024
Raocai 36140 0.024
Raocai 41238 0.024
Raocai 43098 0.024
Raocai 43210 0.024
GiaHoi 0 0.028
GiaHoi 1010 0.028
GiaHoi 3006 0.028
GiaHoi 3061 0.028
GiaHoi 5429 0.028
GiaHoi 7888 0.024
GiaHoi 17624 0.024
GiaHoi 20869 0.024
GiaHoi 23294 0.024
GiaHoi 27864 0.022
GiaHoi 32229 0.022
GiaHoi 33131 0.022
GiaHoi 33210 0.022
Các file đính kèm theo tài liệu này:
- msc_thesis_tran_ngoc_huan_submit_a_affair_library_0234_2085166.pdf